House drainage work (6/9/19 - 6/10):
Trenching work for electric, sewer and drainage (6/21 - 6/30):
Backfill by septic (7/20):
Lots of trimmer work (8/21 - 8/24):
Smoothing ground north of sidewalk (8/24 - 8/30):
Starting backfill on east of house (9/2):
Starting backfill behind house (9/2 - 9/9):
Killing grass where not needed (9/9):
Continue backfill behind house and under A/C (9/10):
Grass planted north of sidewalk (9/10):
Continue ground work behind house (9/12 - 9/15):
Grass planted behind house up to dirt pile (9/16 - 9/22):
Started work on south side of driveway (9/23 - 9/24):
Backfill on west side of house and preparation for major gravel and dirt moving (10/1 - 10/4):
Pastor Dan Phillips moving gravel pile and dirt pile behind house (10/5):
Finish ground work and grass planting behind house (10/5 - 10/8):
Finish ground work and grass planting east of house (10/9 - 10/12):
Moving sod, finish ground work and grass planting south of driveway (10/12 - 10/16):
Clearing brush (10/20 - 11/3):
Second grass cutting of early grass, finished planting grass on west of house (11/3 - 11/4):
Gutter and downspouts plus final drainage and dirt work (11/22 - 11/25):