Customer Needs:  

Size:  4860 sqft

Construction Duration:  Jan. 10 to May 16, 1999

 

Estimated Cost

dig & backfill 4500    gutters 900    electrical labor 4000
gravel 4000 trim materials 3200 special doors 2500
trenching (elec.) 500 trim labor 6000 baptistery 4000
drain tile 2100 drywall 9000 pews & pulpit 10000
building materials 52000 flat work 2000 sound system 4200
framing labor 21000 landscaping 1800 steeple 2000
flooring 12000 plumbing 6000 sign 2500
insulation 2500 HVAC 9000 basement ceilings 4500
roofing 4300 electrical 7000 misc. 2000

Total:  $183,500

Actual Cost

labor 47,800    gravel / concrete 3,350
food for workers 815 carpet 5,050
building materials 41,300 alarm system 1,550
heat / air 14,700 audio equipment 500
furniture 13,200 equipment rentals 420
baptistery 1,540 culverts 870
trusses 11,900 song books 920
crane rental 930 chairs / tables 2,020
doors 2,000 cabinets 2,620

Total:  $152,000
parking lots later paved for $30,700

 

click to enlarge
existing basement
new upper floor
removing temporary roof
wall framing
roof framing
siding
wiring
insulation & hvac
drywall
painting
trim
parking lots