Church 4
Customer Needs:
add upper floor to existing basement structure
initially size sanctuary for 300 people
use non-load bearing walls for upper-floor classrooms and offices, which can eventually be removed to enlarge sanctuary to 500 people
Size: 4860 sqft
Construction Duration: Jan. 10 to May 16, 1999
Estimated Cost
dig & backfill 4500 gutters 900 electrical labor 4000 gravel 4000 trim materials 3200 special doors 2500 trenching (elec.) 500 trim labor 6000 baptistery 4000 drain tile 2100 drywall 9000 pews & pulpit 10000 building materials 52000 flat work 2000 sound system 4200 framing labor 21000 landscaping 1800 steeple 2000 flooring 12000 plumbing 6000 sign 2500 insulation 2500 HVAC 9000 basement ceilings 4500 roofing 4300 electrical 7000 misc. 2000 Total: $183,500
Actual Cost
labor 47,800 gravel / concrete 3,350 food for workers 815 carpet 5,050 building materials 41,300 alarm system 1,550 heat / air 14,700 audio equipment 500 furniture 13,200 equipment rentals 420 baptistery 1,540 culverts 870 trusses 11,900 song books 920 crane rental 930 chairs / tables 2,020 doors 2,000 cabinets 2,620 Total: $152,000
parking lots later paved for $30,700
click to enlarge existing basement new upper floor removing temporary roof wall framing roof framing siding wiring insulation & hvac drywall painting trim parking lots