Problem 4.28
Roof Loads
D = 3 k
Lr = 5 k
Floor Loads
D = 6 k
L = 10 k
W = 10 k
Load Combinations
ASCE 7
EquationIBC
EquationASD Load Combination Load (kip) Shortest-
Duration LoadCD Load / CD* (kip) 1 16-8 D + F 9 D 0.9 10 2 16-9 D + H + F + L + T 19 L 1.0 19 3 16-10 D + H + F + (Lr or S or R) 14 Lr 1.25 11.2 4 16-11 D + H + F + 0.75(L + T) + 0.75(Lr or S or R) 20.25 Lr 1.25 16.2 5 16-12 D + H + F + (W or 0.7E) 19 W 1.6 11.9 6 16-13 D + H + F + 0.75(W or 0.7E) + 0.75L + 0.75(Lr or S or R) 27.75 W 1.6 17.3 7 16-14 0.6D + W + H 15.4 W 1.6 9.6 8 16-15 0.6D + 0.7E + H 5.4 D 0.9 6 * See textbook section 4.24 for explanation/limitations of this shortcut.
NDS Table 2.3.2
Load Duration CD Typical Design Loads permanent 0.9 dead load ten years 1.0 occupancy live load two months 1.15 snow load seven days 1.25 construction load ten minutes 1.6 wind/earthquake load impact 2.0 impact load